Tile, electric, doors
Planet Hardwoods spends many days sanding the floors - then they apply two of the three coats of finish. We will have them back in January to apply the last coat (after all the other workmen tromp all over the floors and scratch them up).
The tile work continues in the three bathrooms and back entryway. About 75% of the tile work is completed, with the last portion scheduled for the week of the 29th.
I spent the last week connecting up devices to all the rough wiring: electric switches, recepticles, fixtures, lighting cans, phone outlets, cable TV outlets . . . etc.
My doors have been delivered, and I have hung a few. During the next few days, I will finish hanging the doors and the plumbing of sinks, toilets, tubs will start.